DISTRICT 27

CUMBERLAND COUNTY I-40 resurfacing from near Plateau Road (MM 311) to near the Obed River (MM 318): Nightly lane closures on I-40 from MM 311 to MM 317 in both directions between 7:00 PM and 6:00 AM. Work consisting of resurfacing. Drivers should use caution when vehicles are entering and exiting the work zone.

[Rogers Group, Inc./Crossville/CNW084]

CUMBERLAND COUNTY SR-1 (US-70) resurfacing from LM 13 (west of SR-24) to LM 16.3 (east of Village Way) including SR-24 east of Obed Street: Construction crews will be on site to perform construction related activities along SR-1 (US-70) that require the outside lane of SR-1 (US-70) from LM 13 to LM 16.3 to be closed from 7:00 PM to 6:00 AM Sunday night through Thursday night. Drivers should use caution when traveling through the work zone.

[Rogers Group, Inc./Crossville/CNW201]

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): Construction signs and erosion control measures have been installed. The contractor continues grading activities which will include embankment fill, storm drain installation, and placement of graded solid rock. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Utility relocations for gas, water, sewer, and electric are in progress. Drivers should use caution while traveling through the work zone and be aware of reduced speed zones.

[Jones Bros. Contractors, LLC/Crossville/CNV009]

CUMBERLAND COUNTY SR-28 (US-127S) repair of the bridges over the Little Obed River (LM 16): Crews will be on site installing construction signs. After signs are installed, the road will be reduced to one lane in each direction through the project.

[Whaley Construction, LLC/Crossville/CNW237]

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction activities are in progress. Activities will require temporary lane closures and/or traffic stoppages on Interstate Drive and Genesis Road as well as short term closures of City streets. The right lane of southbound Genesis Road is closed from Interstate Drive to north of Woodlawn Road. Crews will be working along Genesis Road.

[Rogers Group, Inc./Crossville/CNV010]

CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor will be on site continuing utility work along SR 28 in Cumberland County. Drivers are encouraged to use caution and obey posted speed limit through the construction zone. The contractor will have equipment and personnel adjacent to the roadway during this work.

[Jones Bros. Contractors, LLC/Moore/CNV300]

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Drivers should use caution while traveling through the work zone and be aware of construction personnel.

[Twin K Construction/James/CNV012]

DEKALB AND WARREN COUNTY SR-56 construction of bridges and paving from south of Warren-Dekalb County line (LM 24.5) to East Bryant St. (LM 2.9): The contractor will continue installing concrete box culverts and drainage structures. Grade work, bridge work, and paving operations on the new roadway alignment are ongoing. The contractor is utilizing flagging operations throughout the project in multiple areas for grading operations. Drivers should use caution at the intersection of SR-56 and SR-288 and be mindful of the new traffic pattern. There is a traffic shift between LM 24.4 in Warren County through LM 1.0 in Dekalb County. There is a detour in place for Sink Creek Road. Traffic has been shifted onto the detour between SR-288 and Old Blue Springs Road for the contractor to complete grade work in the area. There are several traffic shifts within Smithville City Limits from South College Street to the end of project to allow contractor to complete work. The speed limit has been reduced to 45 mph in the construction zone.

[Jones Bros. Contractors, LLC/Harris/CNT011]

FENTRESS COUNTY SR-28 (US-127) resurfacing from south of Sawmill Ridge Road (LM 24.6) to north of Squirrel Flat Road (LM 26.3) and from south of Dry Branch (LM 27.9) to north of Joe York Road (LM 29.7): The contractor is scheduled to begin resurfacing operations 08/17/22. During this time, the contractor will utilize lane closures and flaggers to control the flow of traffic through the work zone. Drivers are encouraged to use caution and be prepared to stop as they approach.

[Rogers Group, Inc./James/CNW193]

JACKSON COUNTY SR-477 resurfacing from SR-290 (LM 0) to SR-135 (LM 5.4): The contractor continues resurfacing throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Drivers should use caution while traveling through the work zone and be aware of construction personnel.

[Asphalt Paving Systems, Inc./James/CNW017]

JACKSON AND PUTNAM COUNTY SR-135 resurfacing from south of Kinniard Rd (Putnam) to north of Spring Creek Rd (Jackson): The contractor continues resurfacing activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Drivers should use caution while traveling through the work zone and be aware of construction personnel.

[Asphalt Paving Systems, Inc./James/CNW017]

OVERTON COUNTY SR-85 (HILHAM HWY.) Utility Work both directions from LM 4.52 to LM 3.2: Mobile lane closures along SR-85 between Old Standing Stone Road and Jerry Bilbrey Lane. Drivers should use caution and be aware of personnel and equipment when traveling through the work zone. Signage, cones, and flaggers will be present, 02/17/22 through 08/30/22 between 9:00 AM and 2:00 PM. [2021-457]

OVERTON AND PUTNAM COUNTY SR-164 resurfacing from west of Hassler Road (LM 3.2) to west of Roger Norrod Lane (LM 8.7) and on (SR-24) US-70 from near I-40 (LM 37) to the Cumberland County line (LM 40.3), including bridge expansion joint repair: The contractor will be installing construction signs throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Drivers shall use caution while traveling through the work zone and be aware of construction personnel.

[Rogers Group, Inc./James/CNW215]

PUTNAM COUNTY SR-135 (BURGESS FALLS RD.) Utility Work both directions from LM 3.25 to LM 5.57: Shoulder and single lane closures from Cane Creek Road to the intersection of Cookeville Boatdock Road and Burgess Falls Road. Drivers should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 02/17/22 through 08/30/22 from 9:00 am – 2:00 pm. [2021-771]

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities including installation of barrier rail. Utility relocations are in progress. Drivers should use caution while traveling through the work zone and be aware of construction personnel.

[Rogers Group, Inc./James/CNV284]

PUTNAM COUNTY SR-164 (S. Chestnut St) at LM 0.3 and SR-84 (S. Holly St) at LM 9.7 railroad crossing improvements: The contractor has completed all paving operations. The contractor will be on site intermittently to complete remaining items of work. Temporary lane closures may be used to control traffic through the work zone. Drivers are encouraged to use caution through the work zone and watch for equipment and personnel adjacent to the roadway.

[Stansell Electric Company, Inc./Moore/CNV072]

PUTNAM COUNTY SR-24 (US-70N) construction at the intersection of SR-56 (LM 11.6) in Baxter: During this work, the turning lane from SR 56 north onto SR-24 (US-70N) will be closed. Drivers will be allowed to make the right turn from the four-way intersection. The turning lane from SR-56 to 1st Avenue will also be closed; drivers will be allowed to make the right turn from SR 56 south. The right turn lane on SR-56 south will also be closed; drivers will be allowed to turn right on SR-24 (US-70N) from the four-way intersection. Drivers are encouraged to use caution through the work zone and to watch for construction equipment and personnel adjacent to the roadway.

[Rogers Group, Inc./Moore/CNV098]

WHITE COUNTY SR-136 resurfacing from the Warren County line (LM 0) to SR-135 (LM 15.7): The contractor continues resurfacing throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Drivers should use caution while traveling through the work zone and be aware of construction personnel.

[Asphalt Paving Systems, Inc./James/CNW060]

 

DISTRICT 28

BLEDSOE COUNTY SR-28 (US-HWY. 127) Utility Work southbound from LM 0.01 to LM 9.3: Mobile lane closures along SR-28 between the intersection of US-127 and Kelly lane and the intersection of US-127 and Old Union Road. Drivers should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 06/16/22 through 09/15/22 from 9:00 am – 2:30 pm. [2022-270]

BLEDSOE AND RHEA COUNTY SR-443 from SR-30 (LM 0) to near New Harmony Rd (LM 3.9) and in Rhea from the county line (LM 0) to SR-30 (LM 6.8): During the da, the contractor will be resurfacing and performing safety improvements at two locations on SR-443 in Bledsoe and Rhea Counties. The SR-443 Bledsoe County location will be from SR-30 (LM 0.00) to Near New Harmony Rd (LM 3.93). The SR-443 Rhea County location will be from the Bledsoe County Line (LM 0.00) to SR-30 (LM 6.87). Traffic will be reduced to one lane controlled by flaggers at each location. Drivers should use caution when driving through the work zones.

[Rogers Group, Inc./Voiles/CNW124]

CANNON COUNTY SR-1 (US-70S) from east of SR-145 (LM 6.1) to east of Cummings Hollow Road (LM 9.6): The contractor will be utilizing lane closures with flaggers to complete the resurfacing work from 6:00 AM - 7:30 PM daily between LM 9.6 - LM 6.62. Drivers should use caution and expect delays through the area during this time. Beginning on Sunday 08/21/22, the contractor will close SR-1 nightly from LM 6.62 through LM 5.79 between the hours of 9:00 PM and 6:00 AM to complete milling operations. During these nightly closures, traffic will be detoured onto West Adams Street and SR-53.

[Tinsley Asphalt, LLC /Harris/CNW165]

CANNON COUNTY SR-53 resurfacing from north of Oak Ridge Drive (LM 9.0) to south of Holly Lane (LM 12.0): The contractor will be utilizing daily lane closures and flaggers to complete resurfacing work through the project. Drivers should use caution and watch for flaggers in the work zone.

[Tinsley Asphalt, LLC /Harris/CNW166]

CANNON AND WARREN COUNTY SR-1 (US-70S) bridge repair and paving from east of Lincoln Lane (LM 11) in Cannon County to Robinson Road (LM 9.4) in Warren County: The contractor will be using lane closures daily to complete bridge work. Drivers should use caution through the area.

[American Pavements, Inc./Harris/CNV075]

COFFEE COUNTY I-24 TDOT Maintenance both directions from MM 124 to MM 116: Shoulder closure only: TDOT will be close the shoulder of the interstate in Coffee county for a right-of-way clearing crew (contractor) as per the following below: I-24 West from MM 123.5 to MM 111.5: Wednesday 08/17/22 through Monday 08/22/22, I-24 East from MM EB 117 to MM 122: Monday 08/22/22 through Friday 08/26/22

COFFEE COUNTY SR-127 bridge construction over Bradley Creek (LM 4.7): Construction on this project continue. SR-127 at MM 4.66 will be closed until 09/30/2022 to support bridge construction work over Bradley Creek. A detour will be provided via Prairie Plains Road and Miller Crossroads Road during construction work, signs and message boards are in place to show the detour route. Drivers should be alert to the new traffic pattern and encouraged to use caution and be alert to construction personnel and equipment

[Dement Construction Company, LLC/Hussein/CNV303]

COFFEE COUNTY SR-2 (US-41) repair of bridge over Blue Spring Creek (LM 21.0): Construction on this project continues. The roadway will be reduced to one lane controlled by a temporary traffic signal. One lane will be open to traffic with the restriction of all wide loads, the maximum lane width is 12 feet. Drivers should be alert to a new traffic pattern and encouraged to use caution and be alert to construction personnel and equipment.

[Mid-State Construction Company, Inc./Hussein/CNV145]

FRANKLIN COUNTY SR-130 resurfacing near High Street (LM 13.2) to near SR-15 (US-64 / LM 14.3): During this reporting period, the contractor will have intermittent lane closures on SR-130 to perform resurfacing and roadway repair operations. Drivers are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.

[Tinsley Asphalt, LLC /Hussein/CNW085]

FRANKLIN COUNTY SR-15 (US-41) intersection improvement at University Avenue (LM 27.9): The contractor may have intermittent lane closures to complete punch list work. Drivers should proceed with caution through the area and be aware of signage, personnel, and equipment.

[Dement Construction Company, LLC/Hussein/CNV062]

FRANKLIN COUNTY SR-15 (US-41A) resurfacing from west of Sherwood Road (LM 27.2) to the Marion County line (LM 31): Construction will begin this week; the contractor will install construction signs and perform resurfacing work. Drivers are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.

[Tinsley Asphalt, LLC /Hussein/CNW086]

FRANKLIN COUNTY SR-279 resurfacing from SR-16 (US-41A) (LM0.0) to near SR-127 (LM 5.3): Construction will begin this week; the contractor will install construction signs and perform resurfacing work. Drivers are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.

[Tinsley Asphalt, LLC /Hussein/CNW125]

FRANKLIN COUNTY SR-433 (US-64) resurfacing from near SR-15 (US-64) to SR-50 (US-64) and on SR-50 (US-64) from US-64 (SR-433) to west of Rutledge Ford Road: Construction will begin this week, the contractor will have lane closures on US64 to perform bridge repair work. Drivers are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.

[Asphalt Paving Systems, Inc./Hussein/CNW123]

GRUNDY COUNTY I-24 TDOT Maintenance eastbound from MM 127 to MM 128.6: Eastbound traffic will be reduced to one lane beginning at 6:00 PM 08/18/22 through midnight for pavement patching operations.

MARION COUNTY I-24 (US-64) rockfall mitigation westbound between MM 136.2 and MM 140.3: The contractor will be working on I-24 West at MM 141 – 140, MM 139.0 – 137.0, and MM 136.0 – 135.0. On Thursday 08/18/22 the contractor will set up a single lane closure in lane one on I-24 near MM 136 to repair damaged barrier rail. The lane closure will begin at 9:00 AM CT and be picked up by 1:00 PM CT. Tennessee Highway Patrol and a truck mounted attenuator w/ message board will be on site during this work. Travel lanes at all the other sites have been shifted and are open to traffic. Please use caution when traveling through the work zones.

[Wright Brothers Construction Company, Inc./Voiles/CNV912]

MARION COUNTY I-24 resurfacing from west of Martin Springs Road Exit (MM 141) to east of Big Fiery Gizzard Creek (MM 146): The contractor will continue resurfacing operations on I-24 from MM 140.8 (West of the Martin Springs Rd exit) to MM 146.0 (East of Fiery Gizzard Creek). Work will take place Sunday through Friday from 7:00 PM – 6:00 AM each night in both directions and will close down one lane at a time. Tennessee Highway Patrol and a truck mounted attenuator w/ message board will be on site each night.

[Rogers Group, Inc./Voiles/CNV314]

MARION COUNTY SR-2 (US-HWY. 41) TDOT Contractor both directions from LM 25.7 to LM 26: The roadway is reduced to one lane for slide repairs with temporary traffic signals in place.

MARION COUNTY SR-27 between LM 26.9 and LM 27.9 slide repair and bridge and retaining wall construction: The contractor will be working on SR-27 (Suck Creek Road) at LM 26.9 and LM 27.9 to construct a new bridge and repair a slide. Both work zones, at LM 26.9 and LM 27.9, have the road reduced to one lane controlled by temporary traffic lights. Please use caution when traveling through each work zone.

[Dement Construction Company, LLC/Voiles/CNV307]

MARION COUNTY SR-283 (STATE HWY. 283) TDOT Maintenance both directions from LM 4.1 to LM 4.35: the road will be completely closed to through traffic starting 8:15 AM Central Time through 4:15PM Central time on Thursday August 25th, 2022. Pipe has failed and is being replaced.

SEQUATCHIE COUNTY SR-28 (US-127) Utility Work southbound from LM 9.31 to LM 11.16: Mobile lane closures along SR-28 between the intersection of US-127 and Kelly lane and the intersection of US-127 and Old Union Road. Drivers should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 06/16/22 through 09/15/22 from 9:00 am – 2:30 pm. [2022-270]

SEQUATCHIE COUNTY SR-8 (TAFT HWY.) Utility Work southbound from LM 4.84 to LM 2.53: Shoulder and single lane closures from Progress Lane to Clear Brooks Drive. Drivers should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 08/11/22 through 08/15/22 from 9:00 am – 2:00 pm. [2022-488 & 2022-491]

VANBUREN COUNTY The repair of the bridge on Park Road over Fall Creek Falls Dam Overflow: The contractor will be repairing the Fall Creek Falls dam overflow bridge. The road has been reduced to one lane controlled by temporary traffic signals, and the lane has been painted to direct traffic. Please use caution when traveling through the work zone.

[Mid-State Construction Company, Inc./Voiles/CNW128]

WARREN COUNTY SR-1 (W. MAIN ST.) TDOT Bridge Maintenance eastbound at LM 10.53: Region 2 Bridge Repair will be performing routine maintenance on the West Main Street bridge over SR-55 in the eastbound direction on 08/22/22. Special equipment needed to access portions of the bridge will require temporary lane closures of the left-hand lanes and shoulders.

 

DISTRICT 29

BRADLEY COUNTY I-75 resurfacing from north of SR-311 (US-74 / MM 21) to north of SR-60 (MM 25.5): During this reporting period, the contractor will have lane closures nightly from 7:00 PM to 6:00 AM Sunday night through Friday morning in both directions on I-75 to support resurfacing operations. The speed limit will be reduced to 60 mph while workers are present. Drivers are advised to reduce speed in the work zone.

[Talley Construction Company, Inc./Wagner/CNW045]

BRADLEY COUNTY SR-2 (US-11) resurfacing from Old Highway 11(LM 18.2) to near the Hiwassee River (LM 20.9): During this reporting period, the contractor will have lane closures on SR-2 (US-11) to work on curb ramp installation. Shoulders and sidewalks will also be closed through Charleston for curb ramp upgrades. Drivers are asked to reduce speed in the work zone and watch for flaggers assisting with traffic control.

[Wright Brothers Construction Company, Inc./Wagner/CNW158]

BRADLEY COUNTY SR-312 (HARRISON PK.) TDOT Maintenance both directions from LM 3.1 to LM 3.2: During this reporting period, TDOT maintenance forces may have temporary lane closures on SR-312 between the hours of 8:00 AM and 5:00 PM to continue repair work on a storm drainpipe. Drivers are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.

[TDOT/Maint - Benton/MAINT]

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will be performing earthmoving operations, utility relocation and storm drainage installation. Crews will also be working on foundations for a new bridge over Candies Creek. Drivers are advised to reduce speed in the work zone, watch for flaggers assisting with traffic control and for trucks entering/leaving the highway. Speed limit through work zone will be reduced from 45 MPH to 35 MPH.

[Summers-Taylor, Inc./Wagner/CNV130]

HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): Williams Street is closed to all traffic at the I-24 underpass to support the installation of new storm drainage structures for the new frontage road. Traffic will still be able to access the ramps to I-24 and US-27, but no through traffic will be allowed on Williams Street between West 21st Street and West 25th Street. Traffic will detour around the closure via West 21st Street and Broad Street. Signs will be posted. The contractor is working on new bridge construction, storm drainage structures, and utility relocation. Chestnut Street is closed at the I-24 underpass and will remain closed until the construction of bridge #2 is complete. Detour routes are posted. The US-27 NB on-ramp at William St. has been closed and it will be closed until the new alignment for this ramp is completed. There will be marked detour signs to use the Broad St. US-27 on-ramp. During this reporting period, there will be one lane closed on Market St from 9:00 AM – 3:00 PM. In addition, beginning on Monday August 22nd, there will be lanes closed in both directions on Broad St. from 9:00 AM – 3:00 PM so the contractor can work on the median on Broad St. On Monday thru Wednesday of this reporting period, there will be one lane closed on I_24 West from MM 178 to MM177 from 9:00 PM – 6:00 AM. On Sunday night, from 9:00 PM – 6:00 AM the contractor will close one lane on I-24 Eastbound Friday from MM 179 to MM177.

[Wright Brothers Construction Company, Inc./Curtis/CNU011]

HAMILTON COUNTY I-75 concrete repair from MM 6.6 to MM 12.8: During this reporting period, traffic will be reduced to two lanes of traffic in both direction so the contractor can repair the bridge ends at MM8.44. This lane closure should last for one month. During this operation, it is recommended that drivers use alternate routes in this area because there will be a possibility of long delays as this work take place. Also, during this reporting period, the contractor will have lane closures in both directions on I-75 from 9:00 PM – 6:00 AM. During these lane closures, the contractor might have to temporarily close some of the interstate entrance and exit ramps.

[Summers-Taylor, Inc./Curtis/CNW046]

HAMILTON COUNTY SR-17 resurfacing from the Georgia state line (LM 0.0) to SR-2 (US-11, US-64, US-72) (LM2.2): Starting this reporting period, the contractor will have intermittent lane closures as they begin working on this project.

[Talley Construction Company, Inc./Curtis/CNW213]

HAMILTON COUNTY SR-2 (DODDS AVE.) Utility Work both directions from LM 10.10 to LM 10.61: Center lane closure on Dodds Avenue from E. Main Street to E. 23rd Street and northbound lane closure from E. 23rd Street/Westside Drive to E. 21st Street. Drivers should reduce speed and be prepared to stop. Signage, cones, and flaggers will be present, 08/04/22 through 08/24/22 from 9:00 am – 2:00 pm. [2019-507]

HAMILTON COUNTY SR-29 (US-27) slide repair between LM 29 and LM 30: During this reporting period, TDOT maintenance and contract forces will have traffic reduced to one lane in each direction on US-27 (SR-29) to continue work on a new retaining wall and slope stabilization. Drivers are advised to reduce speed in the work zone. RESTRICTIONS: Max horizontal clearance 14'.

[GeoStabilization International, LLC /Maint - Chattanooga/MAINT]

HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. The flagging operations will be performed on 08/18/22, 08/19/22, 08/22/22, 08/23/22, and 08/24/22 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment. A portion of Tucker Road has been closed from Spalding Drive to 5400 Tucker Road to allow for grading and utility operations. A portion of Chestnut Creek Road has been shifted to its new alignment to allow for grading and utility operations.

[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]

HAMILTON COUNTY SR-319 (Amnicola Highway) bridge repair over SR-153: The contractor will be performing bridge repair operations on the Amnicola (SR-319) bridge over SR-153. During this project, SR-319 will have lane closures in place. During repair operations at least one lane of traffic shall remain open in both directions. Bridge repair over 153 will be performed between 6am & 6pm. Additionally, there will be nightly lane closures starting 8/21/2022 to 8/25/2022 between the hours of 7pm & 6am. Drivers are advised to use caution in this vicinity and remain aware of construction activities.

[Mid-State Construction Company, Inc./Osbonlighter/CNV053]

HAMILTON COUNTY SR-58 slide repair near LM 17: During this reporting period, the contractor will have SR 58 North at LM 17 reduced to 1 lane for the duration of the project.

[Talley Construction Company, Inc./Curtis/CNW199]

HAMILTON COUNTY SR-8 (RINGGOLD RD.) Utility Work eastbound from LM 1.29 to LM .8: Mobile shoulder and lane closures on Ringgold Road as crews transition work zones between Mack Smith Road and Camp Jordan Parkway. This will also impact the North and South on ramps to I-75. Drivers should reduce speed and be prepared to stop. Signage, cones, and flaggers will be present, 08/22/22 through 08/25/22 from 9:00 am – 2:00 pm. [2019-578]

HAMILTON COUNTY SR-8 (US-41, US-76) Bachman Tubes cleaning: On Thursday Night of this reporting period, the contractor will be close the tunnels from 8:00 PM – 6:00 AM to clean it. There will be a signed detour to navigate around the closure.

[Diamond Specialized, Inc./Curtis/CNW197]

HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be performing operations at the intersection connecting the S.I.A. route, Ferdinand Piech Way, & Volkswagen Dr. The new 4-way signalized intersection has begun operation & traffic has been shifted to the new alignment. Ferdinand Piech Way will still be closed to through traffic. Traveling public should be cautious of the new traffic pattern in effect including a lowered speed limit. The traveling public should also be alert to the entrance and exit of construction vehicles & staff on and around the jobsite and the connecting roadways. Flaggers may be onsite directing traffic.

[Talley Construction Company, Inc./Osbonlighter/CNU221]

MCMINN COUNTY SR-163 resurfacing from near SR-2 (US-11 / LM 2.5) to west of County Road 750 (LM 8.9): During this reporting period, the contractor will have daily lane closures from 7:00 AM to 7:00 PM to perform resurfacing and roadway repair operations. Drivers are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.

[Wright Brothers Construction Company, Inc./Wagner/CNW112]

MCMINN COUNTY SR-2 (CONGRESS PKWY.) Utility Work westbound from LM 12.93 to LM 12.1: Mobile shoulder closure along SR-2 between the intersection of Congress Pkwy and Dennis Street and the intersection of Congress Pkwy and Rocky Mount Road. Drivers should reduce speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 08/15/22 through 04/12/23 from 7:30 am – 5:00 pm. [2022-019]

MEIGS COUNTY SR-58 resurfacing from east of the Hiwassee River (LM 5.8) to east of Roberts Road (LM 15.3): During this report period, the contractor will have intermittent lane closures while performing resurfacing operations. Flaggers will be on-site to assist traffic flow. The traveling public should be aware of construction vehicles entering and exiting the work-zone.

[Rogers Group, Inc./Osbonlighter/CNW130]

POLK COUNTY SR-40 (US-64) bridge over the Ocoee River: During this reporting period, the contractor will have lane shifts and temporary lane closures in place from 8:00 AM to 5:30 PM to perform final cleanup and punch list operations. Drivers are advised to reduce speed in the work zone.

[Charles Blalock and Sons, Inc./Wagner/DB1802]

 

REGION WIDE

REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. Flaggers will assist with traffic control as needed.

[NABCO Electric Company, Inc./Osbonlighter/CNT354]

REGION 2 TDOT Maintenance drainage work: There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to clean rock and debris from ditches on an as-needed basis. One lane will be maintained at all times.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 TDOT Maintenance pothole repair and pavement patching: There will be possible short-term emergency lane closures at various locations in Region 2 in order to repair potholes and patch pavement on an as-needed basis. Depending on location and severity these repairs may be done during the day or at night. In addition to performing the work, regional Operations crews will also provide traffic control.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 TDOT mowing operations: There will be possible short-term lane closures at various locations on interstates and state routes in Region 2 in order to perform mowing activities on an as-needed basis. In addition to performing the work, regional Operations crews will also provide traffic control.

[TDOT/Maintenance/R2MAINT]

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor may have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.

[Cumberland Guardrail, Inc./Harris/CNW127]

REGION 2 The random on-call cable barrier repair on various Interstate and State Routes: The contractor may have short term shoulder closures in order to perform cable rail repair. Both travel lanes will always remain open to traffic on the interstate during any work that is performed.

[LU, Inc./Harris/CNV272]

REGION 2 The random on-call pavement marking and retracing of pavement markings with spray thermoplastic on various Interstate and State Routes: Contractor will be performing mobile operations to retrace pavement markings on various routes throughout Polk County. Drivers should expect temporary traffic stoppages and be alert of construction personnel when traveling through the work zone.

[Reynolds Sealing and Striping, Inc./James/CNW059]

REGION 2 The random on-call pavement marking on various interstate and state routes: Contractor will be performing mobile operations to retrace pavement markings on various routes throughout Bradley County. Drivers should expect temporary traffic stoppages and be alert of construction personnel when traveling through the work zone.

[Reynolds Sealing and Striping, Inc./James/CNV036]

REGION 2 The random on-call signing on various Interstate and State Routes: During the daytime the contractor will be setting up shoulder closures at various locations in Grundy, Franklin, and Marion Counties to install new signs for South Cumberland State Park. A truck mounted attenuator will be on site during this work.

[Superior Traffic Control, LLC/Inc./Voiles/CNV194]

REGION 2 The sweeping and drain cleaning on various Interstate and State Routes: There will be an area wide sweeping operation on selected regional state routes and interstates. This activity will be supported by a mobile lane closure. Hours of activity are Sunday through Thursday night between 8 PM and 6 AM during this reporting period.

[Blevins Enterprises, Inc./Curtis/CNV302]

 

RESTRICTIONS

HAMILTON COUNTY SR-29 (US-27) slide repair between LM 29 and LM 30: Maximum horizontal clearance is 14 feet.

Drivers are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.

Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather. All times are local.

From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any land-line or cellular phone for travel information, or follow us on Twitter at www.twitter.com/TN511 for statewide travel or Chattanooga area alerts @Chattanooga511 or any of TDOT's other Twitter pages. As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text, or talk on a cell phone while behind the wheel.

In 2016, the Tennessee Department of Transportation lost three workers in the line of duty. All three were struck by passing motorists. Those tragedies bring the total number of TDOT lives lost to 112. We don't want to lose another member of our TDOT family. We're asking you to WORK WITH US. To learn more, go to the website at https://www.tn.gov/tdot/work-with-us/.

###

Adblock test (Why?)



"activity" - Google News
August 20, 2022 at 01:08AM
https://ift.tt/vIZSMaQ

Roadway Activity Report for parts of East and Middle Tennessee (August 18 - 24, 2022) - tn.gov
"activity" - Google News